Briarwood Emergency Project
Milled 10” depth, Furnished, installed, compact 6” depth G.A.B. Furnished, installed, compacted 2 1/2 “ 19MM superpave. Furnished,
installed, compacted 1 1/2 “ 9.5 MM superpave. Installed striping.
Removal and disposal of unsuitable soil, additional dept rock for soft areas, and furnished and installed fabric strips.
Prepare sub base& major restoration.